The first order of business was to get the window installed. I was hesitant to order the window until the demo was done just to be sure the conditions were as expected and the rough opening could be made large enough. Luckily, it was and we were able to procure the size of window we had hoped and still fit the header in above it. Surprisingly, the window came in after only about a week and a half after ordering! The installation went without a hitch and after the usual Tyvek tape, sill flashing, Flexwrap corners and drip cap, should be nice and tight.
The new window installed in the opening. (Ignore Mike and his long cardboard tube - I'll get into that later!) |
Here you can see the range hood duct (left duct running up wall), supply duct for the office (right duct running up wall) and kitchen supply duct (lower left, will be under the kitchen sink cabinet). |
On 6/11, we tackled leveling the ceiling. Presumably (and long before our time owning it - probably in the 80's), when the house was raised up to remove the crawlspace and install the full basement, the above kitchen wall didn't end up back at quite the right elevation. It was about 2" higher than the rest of the exterior walls. We corrected this 2" in the kitchen floor, but unfortunately, because of the sequence, the unlevelness still exists upstairs. This means the ceiling is not level. Because our cabinets extend all the way to the ceiling, we needed it level to look correct. In the past we have used 1x3 pine furring strips to level walls, ceilings, etc. But the problem here was that part of the floor was actually too low to fit the furring strip along with 1/2" drywall and still plane out with the new dining room ceiling. So, instead, we ran 2x4 segments perpendicular to the floor joists. This way all these 2x4's would be exactly level and match to the dining room ceiling. As you will see in the pictures, some were practically flush with the bottom of the floor joists, while some were nearly 2" below the floor joists! It was a painstaking process to install about 90 of these blocks, but the end result will be a level ceiling!
Looking across the ceiling at the leveling blocks. These were screwed into the floor joists. The drywall sheets will fasten to these and not the floor joists. |
More leveling blocks. You can sort of see from left to right that the blocks hang further below the floor joists as you head west. The blue beam is what these blocks are all leveling to. |
And here is the worst case scenario in the SW corner of the kitchen. The blocks are about 2" below the floor joists! |
Oh yes, and that picture of the window with Mike sticking in the long cardboard tube. I was working on a ladder/platform reading measurements off to Mike who was outside and would cut the 2x4's to length. Rather than have me get off the ladder all the time and come to the window, Mike had an idea to use this long cardboard tube to pass me the boards while on the platform. It worked great!
Mike improving his reach to pass me the 2x4 leveling boards! |
Using the level technique to level up the second end of the 2x4 block. |
New light for the front door installed! |
Stay tuned for the next update!
Before the construction in the kitchen began, but a rare sighting of Tippy and Shop Kitty in harmony. |
And of course a picture of Owen!
No comments:
Post a Comment